Chronicle of Major Events
2006
Dec
-
12.31The second phase of construction of #3CM cement production line in Fuzhou plant in Fujian began. The second phase of construction of #2 slag powder grinding system began.
-
12.31The first phase of construction in Guigang plant in Guangxi began. The project consists of two sets of clinker production line with 6,000 t/d production capacity and the five sets of cement grinding systems with 150t/hr production capacity.
-
12.31The second phase of construction in Yingde plant in Guangdong began. The project consists of two sets of clinker production line with 6,000 t/d production capacity and the two sets of cement grinding systems with 150t/hr production capacity.
-
12.31The second set of clinker production line with 6,000t/d production capacity and five sets of cement grinding systems with 150t/hr production capacity for the first phase of construction in the Yingde plant in Guangdong were completed.
-
12.31The 2006 annual shareholders' meeting was held to elect the 19th directors and supervisors.